Factors Affecting Cost and Execution Period of Trail Bridge Construction Project in Nyamagabe District, Rwanda

Authors

  • Hategekimana Frederic Mount Kenya University
  • Dr. Eugenia Nkechi Irechukwu Mount Kenya University

DOI:

https://doi.org/10.53819/81018102t5192

Abstract

The general objective of this study was to assess the factors affecting execution period (delays) of trail bridge construction project in Nyamagabe district of Rwanda, in southern Province. The study was guided by the following objectives: To assess the effects of environmental factors on bridge completion period in Nyamagabe district, to assess the effect of financial factors on bridge completion period in Nyamagabe district and to assess the effect of changes on bridge completion period in Nyamagabe district. A sample of 80 individuals was selected from a pool of 396 participants involved in the construction of bridges. The data analysis was conducted using SPSS Version 23, and the primary tool for data collection was a questionnaire. Linear regression analysis was employed to identify the factors that influence the delays in the execution period, with a 95% confidence interval and a statistically significant threshold set at a P-value of less than 0.05. The study revealed a significant negative influence of environmental factors on the completion of bridge construction projects, as evidenced by the regression coefficient of 0.425 and the t-value of -0.343. This statistical significance was confirmed by the p-value of 0.002, which is below the threshold of 0.05. The study also identified that financial issues may have an impact on the timely completion of the project, as indicated by the regression coefficient of -0.142 and the t-value of 1.655. However, the statistical analysis showed that this relationship was not statistically significant, as the p-value of 0.102 is above the significance level of 0.05. Furthermore, the study revealed negative effects of changes that occur during the implementation of bridge projects in Nyamagabe District. This is evident from the regression coefficient of -0.294 and the t-value of -3.318, both of which are statistically significant. The p-value of 0.001 is less than the threshold of 0.05, indicating a significant impact of changes on the project.his study concluded that environmental factors and changes related factors have a negative influence on the project execution. This means that those factors contribute more in the delaying and execution of project. Through this, the project stakeholders should conduct deep situational analysis in order to avoid cost and time overrun.

Keywords: Cost, Execution Period, Trail Bridge Construction Project, Nyamagabe District, Rwanda

Author Biographies

Hategekimana Frederic , Mount Kenya University

Postgraduate Student, Mount Kenya University

Dr. Eugenia Nkechi Irechukwu, Mount Kenya University

Lecturer, Mount Kenya University

References

Ahmad, Z. B., Anigbogu, N. A., & Molwus, J. J. (2018). Peculiarities of Road Projects Cost Overruns. International Journal of Scientific & Engineering Research, 9(6).

Al-Emad, N., Rahman, I. A., Nagapan, S., & Gamil, Y. (2017). Ranking of delay factors for Makkah’s construction industry. Paper presented at the MATEC Web of Conferences. https://doi.org/10.1051/matecconf/201710303001

Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and cost overrun in infrastructure projects in Jordan. Procedia Engineering, 182, 18-24.

Aljohani, A., Ahiaga-Dagbui, D., & Moore, D. (2017). Construction projects cost overrun: What does the literature tell us? International Journal of Innovation, Management and Technology, 8(2), 137. https://doi.org/10.18178/ijimt.2017.8.2.717

Amarkhil, Q., Elwakil, E., & Hubbard, B. (2021). A meta-analysis of critical causes of project delay using Spearman’s rank and relative importance index integrated approach. Canadian Journal of Civil Engineering, 48(11), 1498-1507. https://doi.org/10.1139/cjce-2020-0527

Anderson, K., & Wolter, S. (2022). Trail Competency Framework Project Report.

Aziz, R. F., & Abdel-Hakam, A. A. (2016). Exploring delay causes of road construction projects in Egypt. Alexandria Engineering Journal, 55(2), 1515-1539. https://doi.org/10.1016/j.aej.2016.03.006

Belyaev, A., Gordienko, V., Druzhinin, P., & Evtukov, S. (2020). Mathematical model for selecting the best technology for restoring road construction machines. Paper presented at the E3S Web of Conferences. https://doi.org/10.1051/e3sconf/202016403044

Bista, S. B., & Dahal, R. (2018). Assessment of Low Bidding in Bridge Construction with Special Reference to Nepal. International Journal of Research Granthaalayah, 6, 71-80.

Braimah, N. (2013). Construction delay analysis techniques—A review of application issues and improvement needs. Buildings, 3(3), 506-531.

Brooks, W., & Donovan, K. (2019). Eliminating uncertainty in market access: evidence from new bridges in Rural Nicaragua. Econometrica (in revision). https://doi.org/10.3982/ECTA15828

Budha, P. B., & Joshi, B. R. (2022). An Assessment of Operation and Maintenance of Trail Bridges for Sustainable Mobility in Nepal. Himalayan Journal of Applied Science and Engineering, 3(1), 1-7. https://doi.org/10.3126/hijase.v3i1.46940

Davies, R. (2018). Representing theories of change: Technical challenges with evaluation consequences. Journal of Development Effectiveness, 10(4), 438-461. https://doi.org/10.1080/19439342.2018.1526202

De Silva, M. J., Breuer, E., Lee, L., Asher, L., Chowdhary, N., Lund, C., & Patel, V. (2014). Theory of change: a theory-driven approach to enhance the Medical Research Council's framework for complex interventions. Trials, 15(1), 1-13. https://doi.org/10.1186/1745-6215-15-267

Demirkesen, S., & Ozorhon, B. (2017). Measuring project management performance: Case of construction industry. Engineering Management Journal, 29(4), 258-277. https://doi.org/10.1080/10429247.2017.1380579

Djukic, M., Jovanoski, I., Ivanovic, O. M., Lazic, M., & Bodroza, D. (2016). Cost-benefit analysis of an infrastructure project and a cost-reflective tariff: A case study for investment in wastewater treatment plant in Serbia. Renewable and Sustainable Energy Reviews, 59, 1419-1425. https://doi.org/10.1016/j.rser.2016.01.050

Durdyev, S., & Hosseini, M. R. (2019). Causes of delays on construction projects: a comprehensive list. International Journal of Managing Projects in Business. https://doi.org/10.1108/IJMPB-09-2018-0178

Gamil, Y., & Rahman, I. A. (2017). Identification of causes and effects of poor communication in construction industry: A theoretical review. Emerging Science Journal, 1(4), 239-247. https://doi.org/10.28991/ijse-01121

Ghadiyaram, D., Pan, J., Bovik, A. C., Moorthy, A. K., Panda, P., & Yang, K.-C. (2017). In-capture mobile video distortions: A study of subjective behavior and objective algorithms. IEEE Transactions on Circuits and Systems for Video Technology, 28(9), 2061-2077. https://doi.org/10.1109/TCSVT.2017.2707479

Ghosh, S., & Gupta, A. (2021). Design of Wind and Earthquake Resistant Reinforced Concrete Buildings: CRC Press. https://doi.org/10.1201/9781003083320

Gollin, D., Lagakos, D., & Waugh, M. E. (2014). The agricultural productivity gap. The Quarterly Journal of Economics, 129(2), 939-993. https://doi.org/10.1093/qje/qjt056

Gustafson, T. (2020). The Bridge: Natural gas in a redivided Europe: Harvard University Press. https://doi.org/10.2307/j.ctv2d8qx3s

Harold, K. (2021). Project management: A systems approach to planning, scheduling, and controlling. In: John Wiley & Sons, Inc.

Hatamleh, M. T., Hiyassat, M., Sweis, G. J., & Sweis, R. J. (2018). Factors affecting the accuracy of cost estimate: case of Jordan. Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-10-2016-0232

Heale, R., & Twycross, A. (2015). Validity and reliability in quantitative studies. Evidence-based nursing, 18(3), 66-67.

Heo, M., Kim, N., & Faith, M. S. (2015). Statistical power as a function of Cronbach alpha of instrument questionnaire items. BMC medical research methodology, 15(1), 1-9. https://doi.org/10.1186/s12874-015-0070-6

Karunakaran, S., Malek, M., & Ramli, M. (2019). Causes of delay in construction of highway projects: A review.

Kassa, Y. F. (2020). Determinants of infrastructure project delays and cost escalations: the cases of federal road and railway construction projects in Ethiopia. American Academic Scientific Research Journal for Engineering, Technology, and Sciences, 63(1), 102-136.

Khanna, P. (2016). Connectography: Mapping the future of global civilization: Random House.

Korchagin, A., & Zaycev, D. (2021). Evolution of project management in bridge construction. Transportation Research Procedia, 57, 325-331. https://doi.org/10.1016/j.trpro.2021.09.057

Kothuri, S., Nordback, K., Schrope, A., Phillips, T., & Figliozzi, M. (2017). Bicycle and pedestrian counts at signalized intersections using existing infrastructure: Opportunities and challenges. Transportation research record, 2644(1), 11-18. https://doi.org/10.3141/2644-02

Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016). Factors affecting schedule delay, cost overrun, and quality level in public construction projects. Journal of management in engineering, 32(1), 04015032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391

McDonald, C. D. K. (2020). A Case Study of Management: Bosnian Rail-Trail Bridge Design.

Meng, X., Nguyen, D. T., Owen, J. S., Xie, Y., Psimoulis, P., & Ye, G. (2019). Application of GeoSHM system in monitoring extreme wind events at the forth Road Bridge. Remote Sensing, 11(23), 2799. https://doi.org/10.3390/rs11232799

Mpofu, B., Ochieng, E. G., Moobela, C., & Pretorius, A. (2017). Profiling causative factors leading to construction project delays in the United Arab Emirates. Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-05-2015-0072

Niazi, G. A., & Painting, N. (2017). Significant factors causing cost overruns in the construction industry in Afghanistan. Procedia Engineering, 182, 510-517. https://doi.org/10.1016/j.proeng.2017.03.145

Poltava, A., & Korchagin, A. (2019). Problems of determining the reliable cost of construction in the framework of project management. Paper presented at the Development of the methodology of modern economics, management and education in the context of information and digital trends: Materials of the III Interdisciplinary all-Russian scientific conference.

Rachid, Z., Toufik, B., & Mohammed, B. (2019). Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, 19(5), 371-381. https://doi.org/10.1080/15623599.2018.1435234

Rahman, H., Chen, W., & Hui, J. (2016). Impacts of design changes on construction project performance: insights from literature. Journal of Quantity Surveying and Construction Business, 7(1), 31-54. https://doi.org/10.3923/jas.2013.286.293

Rahman, I. A., Memon, A. H., Karim, A. A., & Tarmizi, A. (2013). Significant factors causing cost overruns in large construction projects in Malaysia. Journal of Applied Sciences, 13(2), 286-293.

Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2022). Causes of delay in the global construction industry: a meta analytical review. International Journal of Construction Management, 22(8), 1395-1407. https://doi.org/10.1080/15623599.2020.1716132

Suwal, A., & Shrestha, S. K. (2016). Causes of delays of motorable bridge construction under postal highway projects, Department of Roads. Journal of Advanced College of Engineering and Management, 2, 85-92. https://doi.org/10.3126/jacem.v2i0.16101

Taplin, D. H., Clark, H., Collins, E., & Colby, D. C. (2013). Theory of change. Technical papers: a series of papers to support development of theories of change based on practice in the field. ActKnowledge, New York, NY, USA.

Tesfa, S. Y. (2016). Analysis of factors contributing to time overruns on road construction projects under Addis Ababa City Administration. International Journal of Science and Research, 5(7), 2181-2187. https://doi.org/10.21275/v5i7.ART2016615

Thakur, N. (2021). Cost Overrun and Time Delay Risk Assessment in Local Road Bridge Construction using Fuzzy Inference System. Pulchowk Campus

Thomas, E., Gerster, S., Mugabo, L., Jean, H., & Oates, T. (2020). Computer vision supported pedestrian tracking: A demonstration on trail bridges in rural Rwanda. PLoS one, 15(10), e0241379. https://doi.org/10.1371/journal.pone.0241379

Zidane, Y. J.-T., & Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business. https://doi.org/10.1108/IJMPB-05-2017-0052

Downloads

Published

2023-06-15

How to Cite

Frederic , H., & Irechukwu, E. N. (2023). Factors Affecting Cost and Execution Period of Trail Bridge Construction Project in Nyamagabe District, Rwanda. Journal of Entrepreneurship & Project Management, 7(5), 21–44. https://doi.org/10.53819/81018102t5192