Influence of Project Monitoring & Evaluation on Completion Time of Mwache Dam and Mukurumudzi Dam on Kwale County

Authors

  • James Munge The Catholic University of Eastern Africa
  • Susan Wasike The Catholic University of Eastern Africa
  • Caroline Mungai The Catholic University of Eastern Africa

Abstract

Dam projects require extremely high technical requirements, human management capabilities and large budgets before starting their construction. Thus, time delivery to undertake project dam from problem identification, design, planning and actual construction is very important. Dam projects in Kenya are often not completed in the time scheduled at. This paper determined the influence of monitoring & evaluation on completion time of Mwache Dam and Mukurumudzi Dam in Kwale County. Descriptive research design was utilized in this study. The target population of the study was 212 comprising of 13 project managers, 45 project super indents, 22 site engineers, 17 financial consultants and 26 community representatives from Mwache Dam and 7 project managers, 39 project super indents, 16 site engineers, 9 financial consultants and 18 community representatives from Mukurumudzi Dam. Data was collected by administering structured questionnaires to dam project personnel. Quantitative data were analyzed with the help of the SPSS software Version 25.0 and both descriptive and inferential statistics were generated. Regression of coefficients showed that is a positive and significant relationship between project monitoring & evaluation and dam project completion for both Mwache Dam (β1=.892, p=0.000) and Mukurumudzi Dam (β2=.850, p=0.000). The study concludes that project monitoring & evaluation influences dam project completion time. The study recommends for the adherence of proper project monitoring and evaluation techniques to ensure timely completion of dam projects. Monitoring and evaluation of the dam need to periodic as it will help identify defects in the construction at the earliest time possible and corrective action taken.

Keywords: Monitoring & evaluation, completion time, Mwache dam, Mukurumudzi Dam, Kwale County

Author Biographies

James Munge, The Catholic University of Eastern Africa

Post Graduate Student, Graduate Business School

School of Business

Susan Wasike, The Catholic University of Eastern Africa

Lecturer, School of Business,

The Catholic University of Eastern Africa

Caroline Mungai, The Catholic University of Eastern Africa

Lecturer, School of Business,

The Catholic University of Eastern Africa

References

Aneesha, K., & Haridharan, M. K. (2017, July). Ranking the Project Management Success Factors for Construction Project in South India. In IOP Conference Series: Earth and Environmental Science (Vol. 80, No. 1, p. 012044). IOP Publishing.

Bickman. L (1987). The functions of program theory. New Directions for Evaluation, 33, 5- 18.

Brousselle, A., & Champagne, F. (2011). Program theory evaluation: Logic analysis. Evaluation and program planning, 34(1), 69-78.

Chen, H. T. (2014). Practical program evaluation: Theory-driven evaluation and the integrated evaluation perspective. Sage Publications.

DiStefano, C., & Hess, B. (2005). Using confirmatory factor analysis for construct validation: An empirical review. Journal of Psychoeducational Assessment, 23(3), 225-241.

Field, A. (2013). Discovering statistics using IBM SPSS statistics. Sage.

Funnell, S. C., & Rogers, P. J. (2011). Purposeful program theory: Effective use of theories of change and logic models (Vol. 31). John Wiley & Sons.

Gar, K. K. (2017). Critical Success Factors of Project Management for Dam Construction Projects in Myanmar (Doctoral dissertation, BRAC University).

Gbahabo, P. T., & Ajuwon, O. S. (2017). Effects of project cost overruns and schedule delays in Sub-Saharan Africa. European Journal of Interdisciplinary Studies, 3(2), 46-59.

Ghaben, R. K. (2015). Assessing innovation practices in project management: the case of Palestinian construction projects (Doctoral dissertation).

Golizadeh, H., Banihashemi, S., Sadeghifam, A. N., & Preece, C. (2017). Automated estimation of completion time for dam projects. International Journal of Construction Management, 17(3), 197-209.

Guyadeen, D., & Seasons, M. (2018). Evaluation theory and practice: Comparing program evaluation and evaluation in planning. Journal of Planning Education and Research, 38(1), 98-110.

Higgins, J. V., Konrad, C. P., Warner, A., Hickey, J. T., & Team, G. F. (2011). A Framework for Monitoring, Reporting and Managing Dam Operations for Environmental Flows at Sustainable Rivers Project Sites.

Hughes, J. M. (2015). U.S. Patent No. 9,002,721. Washington, DC: U.S. Patent and Trademark Office.

Jombart, T., Devillard, S., & Balloux, F. (2010). Discriminant analysis of principal components: a new method for the analysis of genetically structured populations. BMC genetics, 11(1), 1-15.

Kerzner, H. (2019). Using the project management maturity model: strategic planning for project management. John Wiley & Sons.

Loehlin, J. C., & Beaujean, A. A. (2016). Latent variable models: An introduction to factor, path, and structural equation analysis. Taylor & Francis.

Lundin, R. A., Tryggestad, K., Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business, 8(1), pp. 198-214.

Maunda, F., M. & Moronge, M. (2016). Influence of Project Life Cycle Management On Completion Of Public Projects In Kenya: A Case Of Makueni Constituency. The Strategic Journal of Business and Change Management, 4 (9), 162-184.

McClelland, S., & McBer, N. (1980). Project Management Competency Theory. Upper Saddle River, NJ: Prentice Hall.

McDavid, J. C., Huse, I., & Hawthorn, L. R. (2013). Key concepts and issues in program evaluation and performance measurement. Program evaluation and performance measurement. An introduction to practice. Los Angeles: SAGE Publications, Inc, 3- 10.

Mertens, D. M., & Wilson, A. T. (2018). Program evaluation theory and practice. Guilford Publications.

Naidoo, A. (2011). The role of monitoring and evaluation in promoting good governance in South Africa: A case study of the Department of Social Development. (Doctoral dissertation), University of Witwatersrand, Johannesburg.

Nair, R. (2016). Project Management, Leadership and Skills:The Three Gorges Dam – China. University Of Salford, Manchester.

Ndungu, R. W. (2014). Factors influencing the completion time of water projects in Water Service Boards in Kenya: A case of Athi Water Services Board, Kiambu County. University of Nairobi, Nairobi.

Ogolla, F., & Moronge, M. (2016). Determinants of effective monitoring and evaluation of government funded water projects in Kenya: a case of Nairobi County. Strateg. J. Bus. Change Manag, 3(1), 329-358.

Olima, W. H. A., & K'akumu, O. A. (2019). The problems of project implementation:: a post- mortem study of Thika Dam project, Kenya. Habitat International, 23(4), 467-479.

Rogers, P. J., & Funnell, S. C. (2013). Purposeful program theory: Effective use of theories of change and logic models. Jossey-Bass.

Rossi, P. H., Lipsey, M. W., & Freeman, H. E. (2004). Expressing and assessing program theory. Evaluation: A systematic approach, 7, 133-168.

Satankar, P. P., & Jain, A. P. S. (2015). Study of success factors for real estate construction projects. International Research Journal of Engineering and Technology, 2(4), 804- 808.

Sharpe, G. (2011). A review of program theory and theory-based evaluations. American International Journal of Contemporary Research, 1(3), 72-75.

Shihemi, R. (2016). Influence Of Monitoring And Evaluation Tools On Projects Performance Of Building And Construction Projects In Kenyan Public Universities: A Case of the University of Nairobi (Doctoral dissertation, University Of Nairobi).

Tengan, C., & Aigbavboa, C. (2017). Level of stakeholder engagement and participation in monitoring and evaluation of construction projects in Ghana. Procedia engineering, 196(6), 630-637.

Titomet, P. K. (2017). Influence of Monitoring and Evaluation on the Performance of Water Projects in Kenya: a Case of Mwala Water Project, Machakos County (Doctoral dissertation, University of Nairobi).

Weiss, C. H. (1998). Evaluation: Methods for studying programs and policies. Pearson College Division.

Downloads

Published

2020-09-24

How to Cite

Munge, J., Wasike, S., & Mungai, C. (2020). Influence of Project Monitoring & Evaluation on Completion Time of Mwache Dam and Mukurumudzi Dam on Kwale County. Journal of Entrepreneurship & Project Management, 4(3), 34–51. Retrieved from https://www.stratfordjournal.org/journals/index.php/journal-of-entrepreneurship-proj/article/view/568

Issue

Section

Articles